Elevator Pits Project List
| DUECK ON MARINE DR. |
 |
| Location: |
Vancouver, BC |
| Date: |
September, 2000 |
| Product: |
KIM - Krystol Internal Membrane |
| Contractor: |
Ventana Construction |
| Project Manager: |
Tony Zanetti |
| Ready-mix: |
Rempel Bros. Ready-mix |
| Performance: |
During excavation an underground waterway was exposed. The project superintendent had used KIM on previous projects with excellent results so he decided to use KIM for the below grade walls and the elevator pit to avoid any potential water ingress problems. |
|
| SURREY YMCA |
 |
| Location: |
Surrey, BC |
| Date: |
April 2001 |
| Product: |
KIM - Krystol Internal Membrane & Krystol construction joint materials |
| Spec Writer: |
Susan Morris |
| Contractor: |
Bird Construction Company Ltd. |
| Project Manager: |
Rob Ezart |
| Ready-mix: |
Graestone Ready-mix Ltd. |
| Performance: |
Waterproofing materials performing as specified in replacement to membranes and all other waterproofig systems. |
|
| SPERLING STATION |
| Location: |
Burnaby, BC |
| Date: |
2000 |
| Product: |
KIM - Krystol Internal Membrane |
| Contractor: |
Westpro Constructors Group Ltd. |
| Project Mngr: |
Darren Carmichael |
| Ready-mix: |
Kask Bros. Ready-mix Ltd. |
| Performance: |
KIM used to waterproof elevator pit in replacement to membranes and other waterproofing systems. |
|
| COQUITLAM CENTRE EXPANSION |
 |
| Location: |
Coquitlam, BC |
| Date: |
2000 |
| Product: |
KIM - Krystol Internal Membrane |
| Architect: |
Architectura |
| Contractor: |
Stuart Olson Construction |
| Project Mngr: |
Alan Lier |
| Ready-mix: |
Rempel Bros Ready-mix |
| Performance: |
KIM used to waterproof elevator pit in replacement to membranes or other waterproofing systems. |
|
|